This time next year, when the project is completed, we will meet all the electricity we consume from this facility. We will be using 100% renewable electrical energy.
•Capacity of Plant : 125.000 Nm³/h SLA (50.000+50.000+25.000)
•Extension of Project Capacity : 225.000 Nm³/h (75.000X3)
•Investment Cost : 5.2 M Euro
•Modular system
•Recovery Capacity Raw Solvent : 430 kg/h
•Recovery Capacity Acetate : 300 kg/h
•Project Completion date : 01.11.2021
Central Water Cooled System: Pilenpak will establish 1250 kW capacity water cooled chiller in PP2 plant. We will replace the old air cooled un-efficiency chillers with water cooling chiller. We will gain 800.000 kw/year energy and more cooling efficiency.
New generation 100% inspection systems are installed on printing machines
New systems that perform online glue inspection during lamination process
Energy consumption is one of the most important aspect of sustainability activity.
We reduced our average electricity consumption per ton by %33 since 2017.
We reduced our average natural gas consumption per ton by %35 since 2017.
As a solution to increase recycling efficiency, it is
aimed to convert packaging from multi-material films
to mono-material.